added documentation and ADR for release schedule
This commit is contained in:
parent
d6eccc8da5
commit
4119d24149
2 changed files with 34 additions and 0 deletions
|
@ -0,0 +1,28 @@
|
|||
# 19. Role-based Access Control
|
||||
|
||||
Date: 2023-11-02
|
||||
|
||||
## Status
|
||||
|
||||
In Review
|
||||
|
||||
## Context
|
||||
|
||||
Going into our first production launch we need a plan describing what our release cadence for both our staging and stable envirornment will be. Currently, we release to staging whenever there are significant changes made, but we have not been making releases to stable with the same frequency. When deciding what our release schedule would be, we discussed releasing to stable once a sprint compared to releasing once a week.
|
||||
|
||||
## Considered Options
|
||||
|
||||
**Option 1:** Releasing to stable/staging once a sprint
|
||||
Releasing once a sprint would mean that we release the past sprint's work to stable at the end of the current sprint. At the same point, the current sprint's work would be pushed to staging; thus making staging a full sprint ahead of stable. While this is more straight forward, it means our users would have to wait longer to see changes that weren't deemed critical.
|
||||
**Option 2:** Releasing to stable/staging once a week
|
||||
Releasing once a week would follow the same flow but with code being released to staging one week before the same code is released to stable. This would make staging only one week behind stable and would allow us to roll out minor bug fixes and faster with greater speed. The negative side is that we have less time to see if errors occur on staging
|
||||
|
||||
In both of the above scenarios the release date would fall on the same day of the week that the sprint starts, which is currently a wednesday. Additionally, in both scenarios the release commits would eventually be tagged with both a staging and stable tag. Further, critical bugs or features would be exempt from these restrictions based on CISA's discretion.
|
||||
|
||||
## Decision
|
||||
|
||||
We decided to go with option 2 and release once a week once in production. This will allow us to give users features and bug fixes faster while still allowing enough time on staging for quality to be maintained.
|
||||
|
||||
## Consequences
|
||||
|
||||
Work not completed by end of the sprint will have to wait to be added to stable.
|